In the basement, the rebar is being finalized for the new footings at the existing columns. The couplers are being added and inspections are ongoing. The windows are being installed.
The existing footing has been demolished to make way for new footing for the shear wall. The rebar and couplers are being installed where the old footings used to be. On Level 1, the corridior wall insulation has been installed, and the tile backer board is ready to start. The soffit drywall is installed at the ceilings. The classrooms are ready for wall patch along side soffit drywall finish. On Level 2, the soffit drywall is being installed at the ceilings. The demo contractor is removing existing electrical outlets that are no longer being used. The new electrical wall molding is being prefabricated. On Level 3, the fire sprinkler lines are complete. The drywall soffits are also complete on Level 3.
The shoring was installed and existing footings in the basement are currently being demolished. The existing doors are being removed on Level 1 and Level 2, based on the changed order work. The framing is complete, and drywall will be starting for soffits on Level 1 and Level 2. The overhead utilities are complete on Level 2. The overhead utilites and framing are starting on Level 3. The re-roofing of the clay tiles is complete. The sewer change order work in the kiln area is being backfilled.
The basement footing rebar is installed. The Level 1 overhead utilities are complete. The Soffits are complete. The Level 2 overhead utilities are almost complete, soffits are being constructed. The Level 3 utilities are starting. The roofing demo is almost complete and clay tile is half way complete for the 4 different roofs. The Team is working on starting exterior handrail and concrete slab above basement door to pottery room.
The basement footing excavation is under way. The basememnt level sprinklers, overhead plumbing, and overhead electrical are complete. The Level 1 sprinklers & HVAC are complete, overhead electrical is ongoing, and overhead framing for T-bar supports complete. The Level 2 sprinklers and electrical are started, overhead HVAC are complete, and the overhead framing for T-bar supports are complete. The Level 3 demo is complete and the overhead HVAC are started.
In the basement level overhead sprinklers and electrical have started. Overhead plumbing is complete. At level 1 overhead sprinklers, plumbing, electrical, and framing as started. At level 2 overhead electrical and plumbing have started. For level 3, the demo and abatment is now complete. The exterior windows have been removed. Building Modeling coordination is complete.
The new sewer line in the basement is complete. The overhead plumbing and electrical is ongoing in the basement. The Level 1 abetment and demolition is complete. The level 1 overhead mechanical is complete. The Level 2 demolition and abatement is complete and it is now starting on Level 3. The shear wall footing excavation is ongoing. We are currently engineering shoring for the columns.
Salvaging owner items is complete. Cut and cap for each floor is complete. The pre-demo air balancing and test report is complete. Demo and abatement of the basemnet is complete. Demo and abatement is taking place on Level 1. The slab demolition for the new sewer system in the basement has started. The team is currently working through the BIM process.