Restoom and storage building: Painted exterior plaster. Hand dryers were installed. Started installation of coping cap. Final health inspection was passed. Punchlist was started. Signage was installed Pool Equipment and bleachers: Exhaust fans and split system unit was installed. Signage was installed. Existing Pool: Abated pool house. Safed off utilities to existing the pool. Salvaged existing equipment inside the pool house. Existing pool water was drained. Site: Continued installation of the site railings.
Restroom and storage building: Installed restroom partitions. Installed lights and electrical finish. Pool Equipment and bleachers: Installed High Performance Paint. Pool Equipment Started Up. Waterproofed Backwash Pit. Pool: Finalized the installation of the plaster. Were able to fill the pool and completed the pool deck area. Site: Installed Irrigation. Musco Lightpoles Aligned. Poured site flatwork. Installed perimeter fencing. Fire lane asphalt was installed.
Restroom and Storage building: Taped and finished restroom ceilings. Exterior shower tile is complete. Began installing shower fixtures, restroom fixtures and toilet accessories. Pool Equipment and Bleachers: Painted Doors and Frames. Installed door hardware and salto system Pool: Installed Deck drains. Rebar and concrete deck pours are in progress.
Restroom and Storage Building: Sarnafil roof installation occurred. Installed roll up door. Restroom tile is complete. Lath and plaster is complete. Pool Equipment and Bleachers: Sack ad patch complete. Pool Equipment installation began. Fire sprinklers were installed. Pool: Tile and homerun plumbing in progress. Grade pool deck and install rough electrical. Excavate and formed surge pit. Perimeter Fence post and installed seat wall formed.
Restroom and Storage Building: Installed backerboard and began tile at restrooms. Lath and plaster exterior. Pool Equipment and Bleachers: Poured and strip deck. Sack and patched walls. Install Interior plumbing and fire sprinklers began. Pool: Install pool tile and homerun plumbing. Grade pool deck and install rough electrical. Excavate and formed surge pit.
Restrooms & Storage Building: Installed metal stud farming, backing and denshield at paraper roofs. Installed Backing at restrooms. Pool Equipment & Bleachers Building: Installed rebar in preparation for deck pour. Installed drainage and began backfill at the North Wall. Pool: Pulled wires and installed waterproofing at the pool gutter. Began underdrainage system for homerun plumbing.
Restrooms & Storage Building: Installed Roof Drains. Framed Walls at restrooms. Began MEP wall rough-ins. Pool Equipment & Bleachers Building: Underground MEP's competed. Installed Sand and Vapor Barrier.Formed adjacent Site ramp walls and installed rebar. Pool: Poured and strips forms for pool bottom. Installed wall rebar, shotcrete and formed gutters.
Restrooms & Storage Building: Installed vapor barrier and poured SOG. Welded erection plates at drag beams. Grouted under baseplates at Beam pockets. Metal Decking installation began. Pool Equipment & Bleachers Building: Poured walls and stripped formwork. Installed underground conduits. Installed sand, vapor barrier. Pool: Health Department inspection occurred 6/4/21 Backfilled UG plumbing, installed rebar and forming of floor began.
The pool project has 2 separate buildings on either side of the pool itself. Building 1: Completed CMU Installation and final grout lift. Installed Pre-slab UG plumbing. Fine grading for vapor barrier occurred. Building 2: 1st side of forms and bracing were installed for the new building exterior wall. Rebar cages and sleeve penetrations were installed. 2nd side of form installation has begun.
Foundations were poured and CMU block installation was grouted up to 8'. Building 2 foundations were poured and installation of UG Utilities have began. The installation of the UG plumbing has occurred at the pool and the project is anticipating the Health Department inspection for plumbing.
During the month of March, the installation of the shoring was complete. Overexcavation and recompaction of soils at both buildings occurred. Installed underground electrical feeders from existing to new pool. Poured footings and stem walls at the North building during the month.
The project capitalized on the distance learning and immediate commenced on the installtion of underground gas line that followed the fire lane around the school. The connection to the gas company is currently in process. Installation of the underground utilities continued with the storm drain, sewer, and fire line extension to the new pool site being completed. The shoring required for the southern most building began with soldier piles in progress.